Mine Civil Construction & On-Site Installation
video

Mine Civil Construction & On-Site Installation

PRS delivers end-to-end civil construction and on-site installation services for copper hydrometallurgical mining projects. From crushing and leaching through solvent extraction, electrowinning and tailings management, our on-site construction team has hands-on experience building and commissioning complete mining facilities across Africa.
Send Inquiry
Product Introduction

African Site Construction - From Crushing to Tailings Management

 

 

PRS provides complete on-site construction and installation services for copper hydrometallurgy projects across Africa. We work from the early civil works stage through to final equipment commissioning - covering crushing, leaching, solvent extraction, electrowinning and tailings facilities.

 

Our construction model combines Chinese project management and engineering standards with local African labor and materials. The result: lower overall cost, faster delivery, full compliance with local regulations, and real job creation for the communities where we work.


 

 Featured Project: 550,000 m² Tailings Reservoir Lining

 

Location: Africa | Project Period: May 23 – July 1, 2026

 

This large-scale tailings anti-seepage project was fully completed in just 40 days. The scope included one layer of geotextile and one layer of textured HDPE geomembrane, covering a total area of approximately 550,000 square meters across the reservoir base and slopes.

 

The entire reservoir lining project

 

   

Key numbers:

  • Total coverage: ~550,000 m²
  • Lining system: 1 layer geotextile + 1 layer textured geomembrane
  • Construction period: 40 days (May 23 – July 1, 2026)
  • Local workers on site: 44–52 people (including geotextile installation teams)

 

The project was delivered on schedule with full welding quality inspection and leak testing before handover.

 

 

44 local workers on site

52 local workers on site

  • Welding of the Electrolytic Cell Overflow Port

    Welding of the Electrolytic Cell Overflow Port
  • Pipe Welding

    Pipe Welding
  • Installation of Launder by Lifting

    Installation of Launder by Lifting
  • Tailings Dam Embankment Raising and Compaction

    Tailings Dam Embankment Raising and Compaction
  • Grinding and Painting of Sulfuric Acid Tank Floor Plates

    Grinding and Painting of Sulfuric Acid Tank Floor Plates
  • Concrete Pouring for Extraction Workshop Floor Slab

    Concrete Pouring for the Extraction Workshop Floor Slab

 


 

 

Full-Scope Construction Capabilities

 

We handle every stage of hydrometallurgical plant construction:

 

  • Crushing & Leaching

Foundation works, leaching tank fabrication, ore preparation area construction and slurry pipeline installation. We build leaching circuits sized to your ore throughput and designed for long-term corrosion resistance.

 

  • Solvent Extraction Workshop

Mixer-settler tank fabrication with on-site welding, reagent station construction, and full inter-stage piping. Our teams have experience building SX plants of various scales, with proper attention to leak prevention and phase separation performance.

We also handle the civil works for SX buildings - including concrete pouring for extraction workshop floor slabs and structural steel installation.

 

  • Electrowinning Tankhouse


Copper Electrowinning Cell Installation | SX-EW Plant Construction Progress
 

Complete tankhouse construction: cell assembly, anode and cathode installation, cathode stripping machine integration, busbar connection and full piping layout. We deliver ready-to-operate EW facilities built to your production capacity.

Specific works include welding of electrolytic cell overflow ports, pipe welding, and launder installation by lifting.

 

  • Tailings Management

This is one of our strongest areas. We do tailings dam embankment raising and compaction, full reservoir anti-seepage lining, and drainage system construction. Our geomembrane laying teams are experienced with large-scale projects and follow strict welding quality standards.

We also have site video available showing the geomembrane laying process - available on request.

 


 

 

What Sets Our Site Construction Apart

 

  • Lower Cost, Same Quality

By using local labor and sourcing materials locally where possible, we keep project costs well below what you'd pay for a full international construction crew - without cutting corners on engineering standards or quality.

 

  • Efficient Project Delivery

Our project management teams are experienced with African site conditions and know how to keep things moving. The 550,000 m² tailings lining project completed in 40 days is a good example of our execution speed.

 

  • Local Government Compliance

We know the regulatory landscape. All our projects are designed and built to meet local environmental, safety and construction standards - so you don't run into approval issues later.

 

  • Real Local Employment

We don't just fly in a Chinese team and leave. We hire and train local workers for every project. On the tailings lining project mentioned above, we had between 44 and 52 local workers on site at different stages - including geotextile installation teams. This isn't corporate language - it's how we actually work.

 

How PRS Works

 

  • Site survey & design review - We come on site, review your engineering drawings and flag any construction considerations early
  • Mobilization - Core team, equipment and key materials move to site
  • Local team setup - We train local workers for the project scope
  • Phased execution - Construction proceeds per schedule, with regular progress reporting
  • Stage-by-stage inspection - Quality checks at every major stage, not just at the end
  • Commissioning & handover - System testing, operator training and formal project handover

 

Get a Construction Proposal

 

If you have a mining project in Africa that needs civil works, equipment installation or full EPC construction, send us your project scope, capacity requirements and location. We'll put together a detailed proposal with timeline and pricing.

 

→ Talk to our construction team

 

Hot Tags: mine civil construction & on-site installation, China mine civil construction & on-site installation suppliers

Send Inquiry

whatsapp

Phone

E-mail

Inquiry