8,000TPA Copper EW Plant

Project Overview


PRS delivered a fully optimized 8,000 TPA copper electrowinning plant, integrating modular design and energy-saving technologies to minimize operating costs and accelerate project commissioning. This turnkey solution features intelligent layout planning, robust equipment selection, and automated operations to ensure rapid production ramp-up and long-term reliability.

8000tpa copper EW plant-1

8000tpa copper EW plant-2

 

Core Design Parameters

 

Parameter

Specification

Annual Production

8,000 TPA

Current Density

270 A/m² (adjustable 250-300 A/m²)

Current Efficiency

≥ 90%

Operating Days/Year

330 days

Number of Cells

42 cells

 

Technical Highlights & Innovations

 

  • Modular Cell Design: Pre-assembled polymer concrete cells enable parallel installation and phased commissioning, reducing construction time by 30%.
  • Smart Power Management: Central SCR rectifier with <3% current ripple and 10% overload capacity ensures stable operation under varying conditions.
  • Optimized Hydrodynamics: Multi-point electrolyte distribution maintains Cu²⁺ variation <3 g/L across all cells.
  • Integrated Automation: High-speed stripping system (250 plates/hour) with automatic weighing and stacking.
  • Energy Conservation: Low-resistance busbars and optimized cell pitch reduce energy consumption by 15% vs. conventional designs.

 

Key Systems & Equipment

 

  • Cell System: 42 polymer concrete cells (L×W×H: 5000×1200×1450mm)
  • Electrode Package: SS316L cathodes (1.9 m² plating area) + Pb-Sn-Ca anodes
  • Power Supply: SCR rectifier 75V/28kA with transformer protection
  • Circulation System: 330 m³/h pumps (1 operational + 1 standby)
  • Material Handling: Dual-hoist overhead crane + automatic stripping station
  • Emission Control: Cell covers + acid mist extraction system

 

Execution & Commissioning

 

  • Phased Approach: Equipment fabrication paralleled with civil works to compress schedule
  • Quality Assurance: All major modules underwent factory acceptance testing
  • Staged Commissioning: Cell banks energized sequentially to ensure smooth ramp-up
  • Knowledge Transfer: Comprehensive operator training and O&M documentation

 

Performance & Outcomes

 

  • Project Timeline: 14 months from design to commissioning
  • Energy Efficiency: 2,800 kWh/t copper (DC power consumption)
  • Product Quality: Consistent LME Grade A cathode copper
  • Operational Uptime: >95% achieved within first 3 months

 