The short answer is: the stability of your entire electrowinning operation hinges on it. While the focus is often on the cells and their chemistry, the precision installation of the pedestals underneath is what truly determines long-term efficiency and prevents costly downtime. This critical first step ensures perfect alignment, structural integrity, and decades of reliable service.
So, how do you achieve this level of foundational stability? It begins with a meticulous process that blends detailed planning with expert execution. In this guide, we'll walk you through the essential steps of installing pedestals, highlighting the professional standards that safeguard your investment.
Why Pedestal Installation is a Cornerstone of Your Operation
Electrowinning cells are monumental structures, carrying immense weight and highly corrosive electrolyte. The pedestals are the critical interface between the rigid concrete floor and the cells, serving three vital functions:
- Structural Integrity & Load Distribution: They evenly distribute the massive weight of the cell and its contents, preventing point loads that could crack the concrete foundation.
- Precise Leveling: A stable, level base is non-negotiable for optimal electrowinning quality. Even minor deviations can affect the anode-to-cathode gap, leading to inefficient electrowinning, short circuits, and reduced cathode quality.
- Resistance to Environmental Stress: A secure foundation prevents movement caused by thermal expansion, vibration, or even minor seismic activity, ensuring long-term alignment.
A Step-by-Step Guide to Precision Pedestal Installation
Following these steps meticulously is key to a successful installation. The process can be visualized as follows:

Step 1: The Blueprint for Success: Meticulous Planning and Drilling
The foundation of a perfect installation is perfect planning. The most crucial tools at this stage are the general arrangement drawing and the 3D model of your plant.
- Action: Using these detailed plans, accurately mark the exact center points for each pedestal on the concrete floor. Use a laser level and surveying tools for large plants to ensure absolute accuracy across the entire floor area.
- Drilling with Precision: Drill the mounting holes according to the pedestal drawings. A critical and often overlooked specification is the hole depth. While typically 200-300mm, it must be calculated based on the specific length of the mounting sticks provided, the pedestal height, and the depth of the mounting hole in the pedestal itself. Undersized holes compromise strength; oversized holes waste grout and time.
- The PRS Advantage: Our documentation is renowned for its clarity. We provide detailed drawings and installation manuals to eliminate guesswork, ensuring your team can proceed with absolute confidence right from the start.
Step 2: The Pre-Assembly: Creating a Monolithic Unit
This step is about preparing the pedestal off-site, ensuring a perfect anchor system before the critical placement phase.
- Action: Fill the pre-cast mounting holes in the pedestal with a high-strength, non-shrink cement grout. While the grout is still wet, immediately insert the mounting sticks. It is vital to use a jig or a level to ensure they are perfectly perpendicular to the pedestal's bearing surface and centered within the holes. Allow the grout to cure completely as per the manufacturer's specifications, creating a single, solid unit.
- Why it Matters: This pre-assembly is a quality control step. It guarantees that the anchors are fixed at the correct angle and depth, a detail that eliminates the risk of misalignment during the high-pressure final placement.

Step 3: The Final Placement: Where Precision Meets Practice
With the pedestal prepared, the final installation demands care and precision.
- Action: Flip the pedestal 180 degrees so the mounting sticks point downward. Pour a fresh bed of high-strength, non-shrink grout into the pre-drilled holes on the ground. The consistency of the grout is key-it should be fluid enough to flow but thick enough to support the pedestal without floating.
- The Critical Maneuver: While the grout is wet, carefully lower the pedestal into its designated location. The key here is perfect alignment: the mounting sticks must slide seamlessly into the holes in the ground without forcing them, which could disrupt the grout bed.
- Final Touches: Once positioned and leveled, seal the perimeter gap between the pedestal base and the ground with grout. This prevents moisture and contaminants from collecting underneath, which could lead to corrosion or frost damage (in colder climates).

Beyond the Basics: Common Challenges and How to Overcome Them
- Challenge: Grout Contraction. Standard cement mixtures can shrink slightly as they cure, creating a small gap.
Solution: Always use a non-shrink grout specifically designed for precision machinery installation. This ensures full bearing contact between the pedestal and the foundation.
At PRS, we understand that your operation's success depends on the synergy between superior products and expert execution. This guide outlines the ideal process, but we know that real-world conditions vary. That's why our support goes beyond supplying components. We offer technical consultation to review your installation plans and can provide guidance tailored to your specific site conditions. By choosing PRS, you are not just buying pedestals; you are gaining a partner dedicated to the long-term productivity and reliability of your electrowinning plant.